By now, hundreds of SANY wind turbines are being used across the globe, providing local communities with clean, renewable energy. SANY machines feature advanced technology, such as doubly-fed and permanent magnet. And the products have passed various tests before launched, ensuring the performance and quality.
SANY wind turbines boast high productivity and reliability. Its optimal CP operation technology allows the turbine to run with optimal capacity before reaching the rated power. In addition, the overload avoidance technology protects the turbines from damage.
Over the past years, SANY wind turbines generators (WTG) have successfully penetrated the global renewable energy market. Below is a showcase of some of the projects using SANY WTG worldwide.

Ralls Wind Farm
Location: Llano Estacado, Texas, US
WTGs: SE8720 Sany 2.0 MW WTG / 5 sets
Installed Capacity: 10 MW
Grid Connection: July 21, 2011
Availability Factor: 96.30% (2012)

Adama II Wind Farm
Location: 95 km southwest to the Capital Addis Ababa, Ethiopia
WTGs: SE7715 Sany 1.5 MW WTG / 102 sets
Installed Capacity: 153 MW
Grid Connection: May 18, 2015
Estimated Power Supply: 480,000 MWh per year

Liziqing Wind Farm
Location: Luxi County, Yunnan, China
Stage One
WTGs: SE8215-III Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5 MW
Grid Connection: November 13, 2011
Availability Factor: 97.93% (2012)
Stage Two
WTGs: SE8215-III Sany 1.5 MW WTG / 27 sets
Installed Capacity: 40.5 MW
Grid Connection: March 4, 2012
Availability Factor: 98.14% (2012)

Huaneng Siping Wind Farm
Location: Siping, Jilin, China
WTGs: SE8215 Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5 MW
Grid Connection: November 18, 2011
Availability Factor: 97.74 % (2012)

Huaneng Kangbao Wind Farm
Location: Kangbao County, Hebei, China
WTGs: SE8215III Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5 MW
Grid Connection: April 10, 2012
Availability Factor: 98.86 % (2012)

Wudengshan Wind Farm
Location: Zhangbei County, Hebei, China
Stage One
WTGs: SE7715 Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5 MW
Grid Connection: November 31, 2010
Availability Factor: 97.74 % (2012)
Stage Two
WTGs: SE7715 Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5 MW
Grid Connection: June 30, 2011
Availability Factor: 98.30 % (2012)
Stage Three
WTGs: SE9320 / 23 sets, SE11020 Sany 2.0 MW WTG, SE8215 Sany 1.5 MW WTG
Installed Capacity: 49.5MW
WTG Lifting: April 13, 2013

Maoniuping Wind Farm
Location: Ninglang County, Yunnan, China
WTGs: SE8215-H3 Sany 1.5 MW WTG / 33 sets
Installed Capacity: 49.5MW
Grid Connection: September, 2012
Availability Factor: 99.2% (2012)